Corpus Christi’s hurricane-damaged Packery Channel to get $15M in repairs – Riverside, California

Riverside, California 2021-09-18 08:30:12 –

After four years of waiting, Corpus Christi will be able to begin repairing a heavily damaged Puckery Channel in October.

Hurricane Harvey in August 2017 collapsed the embankment on the south side of the waterway and its sidewalk, damaging part of the sidewalk on the north side.

The Federal Emergency Management Agency has awarded the city $ 13.5 million for repairs. Another $ 1.5 million for work will come from the tax increase reinvestment zone on North Padre Island.

The city of Corpus Christi plans to begin repairing a heavily damaged packery channel in October. Hurricane Harvey destroyed the embankment on the south side of the waterway and its sidewalk, and also damaged part of the sidewalk on the north side.

The city began bidding for the project on Tuesday. The city council plans to conclude a contract in October. It is estimated that the construction will take about a year.

“After years of relentless effort, we can celebrate this big milestone. Now that we have the money, we can restore the Puckery Channel to make it an asset that residents and visitors will enjoy for years to come. You can, “says Mayor Paulette M. Guajardo.

Built in 2006, the Package Channel is an artificial pass that separates Padre Island and Mustang Island. You can access the sea from around North Padre Island, which connects the canals.

Mayor Paulette M. Guajard will speak at a press conference on September 16, 2021. The city of Corpus Christi plans to begin repairing a heavily damaged packery channel in October. Hurricane Harvey destroyed the embankment on the south side of the waterway and its sidewalk, and also damaged part of the sidewalk on the north side.

The city was back and forth between FEMA and the Army Corps of Engineers demanding funding to repair the Packery Channel.

In December, the Army Corps’ Galveston district informed the city that the channel would not be eligible for corps funding because the project had no flood risk management benefits, according to city documents.

In August, the city council took administrative steps to restore the Packery Channel, seeking funding from the Federal Emergency Management Agency rather than the Army Corps of Engineers.

The city of Corpus Christi plans to begin repairing a heavily damaged packery channel in October. Hurricane Harvey destroyed the embankment on the south side of the waterway and its sidewalk, and also damaged part of the sidewalk on the north side.

Includes work:

  • Demolition and removal of damaged articulated block mat revetments, concrete walkways and bollard / cable barriers.
  • riprap revetment construction;
  • Placement of riprap as toe protection along the land side section of the two piers.
  • Reset the lip wrap and armor stone blocks that have moved along the two piers.
  • Construction of a new concrete walkway;
  • Construction of drainage channels lined with concrete block mats.
  • Improvement of 5 existing storm drainage.
  • Construction of five new storm drains.
  • Replacement of aluminum railing sections along one pier according to the attached plan and specifications.
Mayor Peter Zanoni will speak at a press conference on September 16, 2021. The city of Corpus Christi plans to begin repairing a heavily damaged packery channel in October. Hurricane Harvey destroyed the embankment on the south side of the waterway and its sidewalk, and also damaged part of the sidewalk on the north side.

“Funds to restore the Packery Channel wouldn’t have come any further, as the island is experiencing significant growth in tourism and economic development,” said Mayor Peter Zanoni. rice field. “A clear example is the public-private development of the Park Road 22 Bridge, which is currently under construction.”

In the fall of 2020, the construction of a $ 2.3 million, 100 x 2,500-foot canal on North Padre Island was completed. The waterway will run under the $ 18 million Park Road 22 bridge that the city is building.

Construction of the Park Road 22 Bridge will begin in October 2020 and is scheduled to be completed in mid-2022.

The city of Corpus Christi plans to begin repairing a heavily damaged packery channel in October. Hurricane Harvey destroyed the embankment on the south side of the waterway and its sidewalk, and also damaged part of the sidewalk on the north side.

Kathryn Cargo tracks opening and development while reporting on the impact of city government decisions.See subscription options and special offers at Caller.com/subscribe..

Related article

more:Corpus Christi’s former Wave Resort Water Park is about to be demolished

more:Do you drive smoothly on the South Padre Island Drive frontage road?Yes it’s happening, says TxDOT

more:Thousands flock to Padre Island’s national coast to release sea turtle hatching

Corpus Christi’s hurricane-damaged Packery Channel to get $15M in repairs Source link Corpus Christi’s hurricane-damaged Packery Channel to get $15M in repairs